June 27, 2026 9:23 PM

Current brick work at the theater in Monstropolis. All bricks to be painted soon in the style or theme of Monsters Inc.

June 21, 2026 8:04 PM

Aerial overview of construction of the Monsters Inc. roller coaster in Disney's Hollywood Studios.

June 21, 2026 8:00 PM

Aerial overviews of current building frame for the Monsters Inc roller coaster in Disney's Hollywood Studios. Multiple floors are developing in this area. Track is starting to be placed for the service floor of the ride. Highest supports are for ride track in the first scene.

June 21, 2026 7:49 PM

Aerial photos of color coded groups of bolts in the foundation of the Monsters Inc. roller coaster building.

June 21, 2026 7:34 PM

Arrows in these aerial photos at the first track bolted to a support for the Monsters Inc. suspended door roller coaster. In Disney's Hollywood Studios. This track is at the likely service floor for the ride. Large supports above are for ride track through the first scene.

June 21, 2026 7:16 PM

Aerial photo of 3 sections of track inside the building frame of the Monsters Inc. roller coaster. • Arrow at suspended track attached to a support. • In front are two curved sections staged on wood. To be bolted soon. This track at the likely service floor for the ride.

June 21, 2026 7:07 PM

An aerial look inside the building frame of the Monsters Inc. roller coaster. Bottom arrow at the first section of suspended rail track bolted to the frame. This track is likely at a lower floor service area of the attraction. Large supports above will hold ride track.

June 21, 2026 6:49 PM

Aerial look at construction of the Monsters Inc. roller coaster. Some of the frame is at full height. At center are 2 curved sections of track that will soon be bolted to the frame. Track at this level for the service area. Look close at center to see a 3rd section of track.

June 21, 2026 6:43 PM

Aerial photos of track that has been raised into the building frame of the Monsters Inc. roller coaster. Not yet bolted in place. Rails resting on wood. This floor likely is the service area of the suspended door attraction.

June 21, 2026 6:32 PM

Aerial photo of construction of the Monsters Inc. roller coaster. Upper level of this suspended door ride will have scene 1's. Tracks to merge into a single routing in the area at top center. Arrow at track pending for a lower floor service area of the ride.

June 21, 2026 6:23 PM

Aerial photo of curved track that has been raised into the building frame of the Monsters Inc. roller coaster. These two track sections are not yet in bolted in place. Rails (for suspended door cars) are resting on wood.

June 21, 2026 5:56 PM

An aerial look back at track sections staged for the Monsters Inc. suspended door roller coaster. Section at left is on stands to keep rails off the ground. As seen 2 days ago, Jun 19. Raised yesterday. Next few aerial photos posted will show these inside the building frame.

June 21, 2026 5:43 PM

Above the clouds aerial photo of EPCOT, Disney's Hollywood Studios (top left), and Disney's Animal Kingdom (top center).

June 20, 2026 6:02 PM

In a very distant photo today it seems like the first section of track is being raised at the Monsters Inc roller coaster. In aerial photo yesterday, possibly the same track staged on ground. In stands at the ends to keep the rails off the ground.