July 19, 2026 11:12 PM

Aerial photo of an inversion under construction at Fast & Furious Hollywood Drift. Underneath is switch track for The Spike.

July 19, 2026 11:08 PM

Aerial photos of an inversion in development at Fast & Furious Hollywood Drift.

July 19, 2026 11:01 PM

Aerial photo of an inversion in development at Fast & Furious Hollywood Drift.

July 19, 2026 9:36 PM

Aerial photo of structural steel recently added at left for Fast & Furious Hollywood Drift. Cars will leave the station through switch track, turning into this scene 1. Possibly entering the second building. Cars exit scene 1 through the switch track again and launch.

July 17, 2026 1:50 AM

Track segments are starting to connect in the CityWalk area of Fast & Furious Hollywood Drift. Arrow where cars will enter after after the first launch

July 16, 2026 3:26 AM

Current view of ends of tracks and supports at Fast & Furious Hollywood Drift near CityWalk. A mystery continues about how all these ends will tie together. Arrows where cars are entering from first launch, and returning to the station.

July 16, 2026 2:57 AM

Current platform construction at the block brake in Fast & Furious Hollywood Drift.

July 14, 2026 1:20 AM

At bottom center is current work at switch track for The Spike in Fast & Furious Hollywood Drift.

July 12, 2026 5:58 PM

Electrical wiring in progress for the motors that convey cars into the unload platform of Fast & Furious Hollywood Drift.

July 11, 2026 1:57 AM

Aerial photo of frame being added for a service platform along a block brake of Fast & Furious Hollywood Drift.

July 11, 2026 1:52 AM

Aerial photos of the development of utility buildings in the Fast & Furious Hollywood Drift construction site. Large ductwork is being installed.

July 11, 2026 12:30 AM

Aerial overview of the Fast & Furious Hollywood Drift construction site. From the CityWalk waterfront to the crane at top center.

July 11, 2026 12:19 AM

Aerial photos of Fast & Furious Hollywood Drift construction behind Music Plaza.

July 10, 2026 11:44 PM

CityWalk view of Fast & Furious Hollywood Drift construction. At center, in distance, is structural frame recently added in front of the second building opening.