Current view of Fast & Furious Hollywood Drift from across the CityWalk lagoon. A 170-ft tall tower is under construction at right. The Spike, where cars will rise to the top and then descend into the rest of the ride.
The aerial archive
A permanent archive of @bioreconstruct’s aerial photos of construction around Walt Disney World and Universal Orlando — full-resolution originals, preserved daily. Every post links back to its source.
- 25,792
- photos
- 21,321
- posts
- spanning
- November 2023 – August 2026
- latest
- August 3, 2026
More filters ↓ Fewer filters ↑
+40 more Fewer
+11 more Fewer
Jump to a month
Front view of structure rising for the 170-ft tall Spike of Fast & Furious Hollywood Drift. Arrow at a line of supports leading to the rise up and back down the tower. Line of supports near footers for switch track.
Photo today of on-the-ground staging of support structure for the Spike of Fast & Furious Hollywood Drift.
Seems like Universal Creative may have planned how the Globe will look when paired in photos with the 170-ft tall Spike of Fast & Furious Hollywood Drift. Current structure for the Spike at center.
Current structure for the 170-ft tall Spike element of Fast & Furious Hollywood Drift.
Aerial photos of roller coaster construction near the former Blue Man Group theater. For Fast & Furious Hollywood Drift.
Aerial photos of Fast & Furious Hollywood Drift construction. A 170-ft tall Spike element is in development. Also track was placed here last week.
Aerial photo of Fast & Furious Hollywood Drift construction. Cars will head down a straight line of track running diagonally from top right toward the waterfront. A 170-ft tall Spike element is in progress. Cars will rise up and then descend into the remainder of the ride.
Aerial photo of construction in progress for the 170-ft tall Spike element of Fast & Furious Hollywood Drift. Also seen is the track placed last week.
Aerial photos of roller coaster footer construction near a switch track platform for Fast & Furious Hollywood Drift. Look closely ... some pilings have been partially excavated. Months ago an auger drilled holes that were filled with concrete. Footers now in progress at pilings.
Aerial photos of Fast & Furious Hollywood Drift construction behind Music Plaza.
At top center of this aerial photo is construction of the service building for Fast & Furious Hollywood Drift. It seems like other kinds of ride vehicle and show maintenance will be supported too.
Aerial photos of track and supports in progress at the station of Fast & Furious Hollywood Drift. Structural frame for the station recently increased too. Trusses for the roof in progress.
Track supports at right were recently added near the station of Fast & Furious Hollywood Drift. There's also additional structural frame for the station.
A nearly straight-down aerial photo of construction at the station of Fast & Furious Hollywood Drift. • Supports recently added for track on other side of the switch track for trains arriving at unload/load. • New concrete at left center where utility work recently completed.