April 24, 2026 11:51 PM

Aerial photo of the Universal Orlando globe and a Water Taxi.

April 24, 2026 11:47 PM

Aerial photo of where Luke Combs' Category 10 will be built in CityWalk. Compare to earlier aerial photo in this Thread. Some kiosks have moved.

April 24, 2026 11:21 PM

Aerial photo of the new Universal Legacy Store in CityWalk. It opened this morning.

April 24, 2026 8:53 PM

Aerial photos of track recently placed at the station of Fast & Furious Hollywood Drift. Station will have a dual load/unload configuration. Track won't go past the switch track platform until station construction no longer needs the crane.

April 24, 2026 8:38 PM

Aerial photos of a recently cast concrete platform near the Fast & Furious Hollywood Drift station. Concrete forms are being prepared for footers of switch track. At center of the second photo, pilings made with an auger will have a footer for track to the service building.

April 24, 2026 8:26 PM

Aerial photo of where Fast & Furious Hollywood Drift is crossing over a longtime utility building near the roller coaster station. Second photo (Apr 10) and third photo (Sep 7, 2025) show this building being preserved.

April 24, 2026 8:08 PM

Aerial overviews of construction of the Fast & Furious Hollywood Drift roller coaster station. Track is seen for a dual load-unload configuration. A second concrete platform was recently cast for switch track accessing the station and also the service building.

April 24, 2026 7:30 PM

Aerial photo showing that a recently started utility project in Universal now spans into the construction site of Fast & Furious Hollywood Drift

April 24, 2026 7:01 PM

Aerial overview of construction at the station of Fast & Furious Hollywood Drift. Track recently placed for the dual load/unload of the attraction. Two concrete platforms are seen for switch track. The platform at top center was recently cast. Ride service building at top right.