April 4, 2026 2:33 AM

Aerial photo of work for an addition to Celestial Park. A multipurpose building that can be used by private events.

April 3, 2026 10:10 PM

Aerial photos of construction of the newest parking garage in Universal Orlando. Along Turkey Lake Rd. Adjacent Loews Hotels offices.

April 3, 2026 10:02 PM

Aerial photo of construction of the newest parking garage in Universal Orlando. In the Southernmost end of the Universal Studios Florida property, along Turkey Lake Rd. Adjacent Loews Hotels offices.

March 28, 2026 11:49 PM

Aerial photo of a viaduct being built, with utilities above the concrete. The road will be rebuilt above. Viaduct allows water to transfer in the Walt Disney World water management system. Sand is being mined in foreground for use in Piston Peak and Villain's land.

March 28, 2026 1:59 PM

Aerial overviews of construction of the village in Tropical Americas. A mix of earth moving and concrete forms. The circular concrete is foundation for the carousel.

March 28, 2026 2:13 AM

Aerial photos of work in progress for the foundation of the Monstropolis roller coaster. Conduit is being threaded through rebar at bottom right. Spray painted lines are seen on the concrete layer. Another layer of concrete will be cast above it.

March 28, 2026 1:52 AM

Aerial photo of the Monstropolis roller coaster foundation preparation. Southwest quadrant. Plywood walkways. Square plates holding bolts for supports. Conduit has been threaded through the rebar. Conduit is also in sand at left, where the load/unload will be for the ride.